Risk
Issue vs risk: what goes in the issue log and what goes in the risk register
A risk is an uncertain event that might happen and would affect your objectives, so it belongs in the risk register; an issue is something that has already happened and needs action now, so it belongs in the issue log. The test is simple: if you can still ask "what if?", it is a risk; if you are asking "what now?", it is an issue.
Issue vs risk: the definitions
A risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one project objective: scope, time, cost or quality. It has a probability below 100% and sits in the future. Negative risks are threats; positive risks are opportunities.
An issue is a current problem, question or condition that is already affecting the project, or will do so with certainty unless someone acts. Its probability is effectively 100%. Issues need an owner, a decision and a date, not a likelihood score.
The two registers answer different questions. The risk register asks what could happen and how prepared you are. The issue log asks what is going wrong right now and who is fixing it. Mixing them hides urgent problems among speculative ones and makes both lists harder to manage.
Side by side comparison
| Question | Risk register | Issue log |
|---|---|---|
| Timing | Future, may happen | Now, has happened |
| Probability | Between 0% and 100% | 100% |
| Main scores | Probability, impact, exposure, EMV | Priority, severity, due date |
| Action | Planned response: avoid, mitigate, transfer, accept (or exploit, enhance, share for opportunities) | Resolution: decide, fix, escalate |
| Review rhythm | Monthly or at each phase, plus when something changes | Weekly or daily until closed |
| Closed when | The window passes or the risk occurs | The problem is resolved and verified |
A useful side effect: when a risk occurs, it becomes an issue. You close the risk (status "occurred"), open an issue that links back to it, and run the contingency plan you already wrote.
Worked examples: sort these five entries
Here is a typical mixed list from a weekly meeting, sorted with the "what if or what now" test.
| Entry | Goes in | Why |
|---|---|---|
| The supplier may deliver the switchgear four weeks late | Risk register | Uncertain and in the future |
| The switchgear delivery date was missed yesterday | Issue log | It has happened; the risk above occurred |
| The client has not approved the design and the next activity starts Monday | Issue log | A decision is needed now |
| A key developer might resign during testing | Risk register | Possible, not certain |
| Exchange rates are volatile | Neither, as written | This is a condition, not an event. Rewrite it as a risk: "If the rate moves more than 5% before we order, material cost may rise by $20,000." |
The last row shows a common trap. Vague statements of worry are not risks until you name a cause, an event and an effect.
Another grey area is the open question. "Which cable size does the client want?" is an issue if work is waiting for the answer, and nothing at all if the answer is not needed for months. Log it when it blocks or will soon block a task, and give it the date by which the answer is needed.
The columns each register needs
Risk register: ID, title written as cause, event and effect; category; threat or opportunity; owner; probability and impact scores (often on a 5×5 matrix); cost and schedule exposure; response strategy and actions; trigger; due date; status. Exposure in money is often expressed as expected monetary value (EMV = probability × impact): a 20% chance of a $50,000 overrun gives an EMV of $10,000.
Issue log: ID, title and description; date raised; raised by; owner; priority (for example high, medium, low); impact on scope, time or cost; action needed; target resolution date; status; linked risk or change request; resolution notes.
Keep the issue log short and blunt. If an issue needs a change to budget, dates or scope to resolve it, raise a change request and link it rather than approving the change inside the issue.
Running both logs: a weekly and monthly rhythm
The two registers work best with different meeting slots.
- Weekly, 15 minutes on issues. Go through open issues by priority. For each one, confirm the owner, the next action and the date. Close anything resolved and verified. Escalate anything that has missed its date twice.
- Weekly, 5 minutes on new risks. Ask the team one question: "what has changed that could hurt or help us?" Add new entries to the risk register with an owner; score them later if needed.
- Monthly, 30 to 60 minutes on risks. Re-score the top risks, check that response actions are happening, look at triggers, and retire risks whose window has passed.
- At every phase or gate. Run a fresh identification workshop, because each phase brings different risks.
When a risk occurs, follow the same short routine each time: set the risk status to occurred, open a linked issue with an owner and date, start the contingency plan, raise a change request if the baseline must move, and later record the actual cost and delay against the original estimate. That last step improves your next set of estimates more than anything else.
Common mistakes
- Logging issues as risks with 100% probability. It inflates the risk register and hides problems that need action this week.
- Never closing risks that occurred. Mark them occurred, link the new issue, and record what the response actually cost.
- Issues without owners or dates. An issue with no owner is a complaint, not a log entry.
- Using the issue log for change approval. Changes to the baseline go through change control.
- Reviewing both lists at the same pace. Issues need a short, frequent cycle; risks need a deliberate, regular review.
How to do this in Critova
Critova keeps the two lists separate on purpose. The risk register shows risks as a list, a board by status or a clickable 5×5 matrix, with owners, responses, due dates, cost and schedule exposure and EMV. Issues and change requests have their own registers, and a change request records its budget and date impact when it is approved or rejected. See the risk features, or read the project risk management guide for the full process.
Common questions
Can an issue become a risk?
Not directly, but an issue can create new risks. A late delivery (issue) can raise the chance of missing a later milestone (new risk), so log that risk separately.
Is an assumption a risk?
An assumption is something you treat as true for planning. If it might turn out false and that would hurt the project, write the matching risk and review it.
Do small projects need both logs?
Yes, but they can be very short: a handful of risks and an issue list reviewed in the weekly meeting is enough.
Bring one schedule. See your critical path in an hour.
Free during our launch until 31 March 2027.