Free during our launch: every feature, every plan, until 31 March 2027.

See the offer

Project management basics

Project charter template: what goes in it, with a filled-in example

A project charter is a short document, usually one to three pages, that formally authorises a project and names its sponsor, project manager, goal, scope, high-level schedule, budget, key risks and success criteria. It should contain just enough for the sponsor to say yes and for the team to start planning, and the template below lists every section with an example.

Updated · 4 min read

What a project charter is for

The charter does three jobs. It authorises the project, so people and money can be committed. It names the project manager and gives them authority to use those resources. And it records a shared understanding of why the project exists and what success means, before anyone writes a detailed plan.

The PMBOK Guide treats the charter as the main output of initiating a project. PRINCE2 covers similar ground in its project brief. Whatever the name, the content is the same: the essentials, agreed and signed by the sponsor.

A charter is not a project plan. It does not list tasks or detailed dates. Those come next, in the work breakdown structure and the schedule. Keep the charter short enough that a busy sponsor reads all of it.

Project charter template

Copy this table into a document and fill in the middle column. The example column uses a customer portal project.

SectionWhat to writeExample
Project nameA short, specific nameCustomer self-service portal, phase 1
Purpose (business case)The problem or opportunity, in two or three sentencesCustomers phone us to check order status. A portal lets them check it themselves and frees support time.
ObjectivesMeasurable outcomes, ideally with a target and a dateCustomers can view orders and invoices online by 30 June; status calls fall measurably within three months of launch
Scope: inThe main deliverablesLogin, order list, order detail, invoice download, English and Arabic pages
Scope: outWhat people might assume is included but is notOnline payment, mobile app store app, changes to the warehouse system
MilestonesFour to eight key datesDesign approved (15 Feb), build complete (30 Apr), user testing done (31 May), launch (30 Jun)
BudgetTotal, with contingency shown separately$85,000 including $8,000 contingency
SponsorThe person who owns the business case and approves changesHead of customer service
Project manager and authorityName, and what they can decide aloneDigital project lead; may approve changes up to $2,000 or one week
Key stakeholdersGroups affected or neededSupport team, IT, finance, a panel of five customers
AssumptionsThings taken as true for planningThe order system can expose data through its existing interface
ConstraintsFixed limitsMust launch before the peak season in July
Key risksThe three to five biggest threats or opportunitiesOrder system interface slower than expected; customer testers unavailable
Success criteriaHow the sponsor will judge the result at closurePortal live, accepted by support, within budget, launched by 30 June
ApprovalSignature and dateSponsor, project manager

How to write a project charter in five steps

  1. Interview the sponsor for 30 to 60 minutes. Ask why now, what happens if the project does not run, what a good result looks like, the budget envelope and the hard deadline.
  2. Draft the purpose, objectives and scope first. These drive everything else. Write the "out of scope" list with the same care as the "in scope" list.
  3. Add rough milestones and budget. Use ranges if you must, and show contingency as its own line so it is visible and approved.
  4. List three to five risks and the key assumptions. An assumption that turns out false often becomes the project's biggest issue, so write them down now.
  5. Review with key stakeholders, then get the signature. A charter that the sponsor has not formally approved does not authorise anything.

Writing objectives that can be checked

The objectives row is where most charters are weakest. "Improve customer experience" cannot be checked at closure. A useful test: could two people independently look at the finished project and agree whether the objective was met? Compare:

  • Weak: "Modernise the warehouse."
  • Better: "Replace the paper picking process with handheld scanners in both warehouses by 31 October, within $120,000."

Include a target and a date, and separate the project objectives (what the project delivers) from the business benefits (what changes afterwards). The project manager controls the first; the sponsor usually owns the second.

Who writes the charter, and when

The sponsor owns the charter, but the project manager (or a business analyst) usually drafts it, because they will live with it. Write it as soon as the project has been chosen and before any detailed planning or spending starts. If people are already working before the charter is signed, the project is running without agreed scope, budget or authority, and every later argument will be harder to settle.

Scale it to the project. A two-month internal project may need a single page covering purpose, scope, dates, budget and sponsor. A multi-year contract may need the full table plus an organisation chart and a summary of the procurement approach. The test is the same in both cases: does it give the sponsor enough to decide, and the team enough to start planning?

Common project charter mistakes

  • Writing a plan instead of a charter. Twenty pages of tasks hide the decisions the sponsor needs to make.
  • No "out of scope" list. Unwritten exclusions become arguments in month three.
  • No named sponsor. A committee cannot approve changes quickly. Name one person.
  • Unclear authority for the project manager. State what they may approve alone, for example changes up to a set amount or a set number of days.
  • Never revisiting it. If the purpose or budget changes materially, update the charter through change control and re-sign it.

How to do this in Critova

In Critova, create the project from one of the project templates, attach the signed charter in the project's files, and copy the milestones and budget into the plan so they become the first baseline. Put the charter's key risks straight into the risk register with owners, and route later scope or budget changes through change requests, which record the budget and date impact and whether the sponsor approved or rejected them. To size the contingency line with ranges instead of a single guess, the three-point estimate calculator is a quick start.

Common questions

How long should a project charter be?

One to three pages for most projects. Large, contract-driven projects may need more, but if the sponsor will not read it in one sitting, it is too long.

Who signs the project charter?

The sponsor signs to authorise the project. The project manager usually signs too, to confirm they accept the role and its limits.

What is the difference between a charter and a business case?

The business case argues whether the project is worth doing, with costs and benefits. The charter comes after that decision and authorises the project, summarising the business case in a few lines.

Bring one schedule. See your critical path in an hour.

Free during our launch until 31 March 2027.