Free during our launch: every feature, every plan, until 31 March 2027.

See the offer

Free calculator

Earned schedule calculator: ES, SV(t) and SPI(t)

Paste the cumulative planned value for each period, then enter the earned value and how many periods have passed. You get the earned schedule, the time variance, SPI(t) and a forecast duration.

Updated · 2 min read

Calculator

Your numbers
Result
Earned schedule (ES), periods
3.25
Schedule variance in time, SV(t)
-0.75Behind plan
Schedule performance index, SPI(t)
0.81
Planned duration (PD), periods
10
Forecast duration, IEAC(t) = PD / SPI(t)
12.3

A period can be a week or a month, as long as every figure uses the same one.

The formulas

ES = C + (EV − PVC) / (PVC+1 − PVC)C is the last whole period where planned value was at or below today's EV
SV(t) = ES − ATschedule variance in time: negative means behind
SPI(t) = ES / ATschedule performance in time
IEAC(t) = PD / SPI(t)forecast duration, where PD is the planned duration

Worked example

A ten-month project plans a cumulative value of 100, 220, 360 and 520 in its first four months. At the end of month 4 the earned value is 400.

The plan reached 360 at month 3 and 520 at month 4, so C is 3 and ES = 3 + (400 − 360) / (520 − 360) = 3.25 months. SV(t) is 3.25 − 4 = −0.75 months, and SPI(t) is 3.25 / 4 = 0.81. At that pace the project takes 10 / 0.8125 = 12.3 months.

The earned schedule guide explains why this is more reliable than SPI late in a project.

Common questions

Why not just use SPI?

SPI is EV / PV in money, and it returns to 1.0 at the end of every project, late or not. SPI(t) measures time, so it stays meaningful to the last day.

Bring one schedule. See your critical path in an hour.

Free during our launch until 31 March 2027.